What drives the percentage of completion for Action Task Types in the development Calendar?

I was under the impression that the % Complete column would be driven by approval of tasks, but the percentage didn't go up when I approved a task type (e.g.: Approved 5 BOMs for styles using the development calendar). Please let me know what needs to happen for that % to go up?

Best Answer

  • Carlina BriscusoCarlina Briscuso Gerber Staff 💛
    Accepted Answer
    @MCruz, hi! :)  Great question!

    The Dev Calendar pulls the status from the Style workflow page (the parent page in the case of TextImage, Measurements, BOM, Care and others that permit multiple pages in the style).

    When a child page is approved, the parent is automatically also approved.

    Let me know if this helps answer the question.